A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Advertisements
उत्तर
Length of canal = 6 km
In 20 days canal made = 2 km
Remaining length of canal = 6 – 2 = 4 km
Remaining time = 35 – 20 = 15 days
In 20 days 2 km canal is made by = 90 men
In 1 day 2 km canal is made by = 90 x 20 men
In 15 days 2 km canal is made by = `(90xx20)/15` men
In 15 days 1 km canal is made by = `(90xx20)/(15xx2)` men
In 15 days 4 km canal is made by = `(90xx20xx4)/(15xx2)` men = 6 x 10 x 4 men = 240 men
Number of more men to be employed to finish the work in time = 240-90 = 150 men
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?