प्रश्न

A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?

योग
Advertisements

उत्तर

Length of canal = 6 km

In 20 days canal made = 2 km

Remaining length of canal = 6 – 2 = 4 km

Remaining time = 35 – 20 = 15 days

In 20 days 2 km canal is made by = 90 men

In 1 day 2 km canal is made by = 90 x 20 men

In 15 days 2 km canal is made by = `(90xx20)/15` men

In 15 days 1 km canal is made by = `(90xx20)/(15xx2)` men

In 15 days 4 km canal is made by = `(90xx20xx4)/(15xx2)` men = 6 x 10 x 4 men = 240 men

Number of more men to be employed to finish the work in time = 240-90 = 150 men

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (D) [पृष्ठ १२९]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (D) | Q 4 | पृष्ठ १२९

संबंधित प्रश्न

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


Share