Length of canal = 6 km

In 20 days canal made = 2 km

Remaining length of canal = 6 – 2 = 4 km

Remaining time = 35 – 20 = 15 days

In 20 days 2 km canal is made by = 90 men

In 1 day 2 km canal is made by = 90 x 20 men

In 15 days 2 km canal is made by = `(90xx20)/15` men

In 15 days 1 km canal is made by = `(90xx20)/(15xx2)` men

In 15 days 4 km canal is made by = `(90xx20xx4)/(15xx2)` men = 6 x 10 x 4 men = 240 men

Number of more men to be employed to finish the work in time = 240-90 = 150 men

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (D) [पृष्ठ १२९]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (D) | Q 4 | पृष्ठ १२९

संबंधित प्रश्न

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×