प्रश्न
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
Advertisements
उत्तर
A can finish a piece of work in = 15 days
B can finish a piece of work in = 10 days
∴ A's 1 day work =`1/15`
B's 1-day work =`1/10`
(A+B)'s 1-day work =`1/15+1/10`
`=(2+3)/30=5/30=1/6`
(A+B)'s 2 days work =`1/6xx2=1/3`
Remaining work which will be done by A alone
`=1-1/3=(3-1)/3=2/3`
∴ A can finish 1 work in = 15 days
A can finish `2/3` work in =`15xx2/3` days
`=30/3`days = 10 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?