22 Men Can Dig a 27 M Long Trench in One Day. How Many Men Should Be Employed for Digging 135 M Long Trench of the Same Type in One Day? - Mathematics

Advertisements
Advertisements

प्रश्न

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?

बेरीज
Advertisements

उत्तर

Men: Length trench:: Men : Length of trench

  22 :      27 m         ::    x    :     135 m

x = `(22xx135)/27`

= 110 men

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (A) [पृष्ठ १२१]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (A) | Q 8 | पृष्ठ १२१

संबंधित प्रश्‍न

A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×