22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?

Sum
Advertisements

Solution

Men: Length trench:: Men : Length of trench

  22 :      27 m         ::    x    :     135 m

x = `(22xx135)/27`

= 110 men

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (A) [Page 121]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (A) | Q 8 | Page 121

RELATED QUESTIONS

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


72 men do a piece of work in 25 days. In how many days will 30 men do the same work?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×