A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?

बेरीज
Advertisements

उत्तर

A can do a piece of work in = 10 days

B can do a piece of work in = 18 days

(A+B+C) can do a piece of work in = 4 days

∴ A's 1-day work =`1/10`

B's 1-day work = `1/18`

(A+B)'s 1-day work =`1/10+1/18=(9+5)/90`

`=14/90=7/45`

(A+B+C)'s 1-day work =`1/4`

∴ C's 1-day work =`1/4-7/45`

`=(45-28)/180=17/180`

∴ C can do the piece of work in = `180/17` days

`=10 10/17` days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 9 | पृष्ठ १३३

संबंधित प्रश्‍न

22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.

  1. How long will it take them to do the work together?
  2. In what time can each finish it working alone?

A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×