A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
Advertisements
Solution
(A+B) can mow a field in = 56 days
(A+B+C) can mow a field in = 42 days
∴ (A+B)'s 1 day work =`1/56`
(A+B+C)'s 1 day work =`1/42`
C's 1 day work =`1/42-1/56`
`=(4-3)/168`
`=1/168` 
L.C.M. = 2 × 7 × 3 × 4 = 168
∴ C can do the work in = 168 days
APPEARS IN
RELATED QUESTIONS
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?