Question
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
Advertisements
Solution
A can do a piece of work in = 6 days
B can do a piece of work in = 12 days
C can do a piece of work in = 24 days
∴ A's 1-day work =`1/6`
∴ B's 1-day work = `1/12`
∴ C's 1-day work = `1/24`
(A+B+C)'s 1-day work =`1/6+1/12+1/24`
`=(4+2+1)/24=7/24`
∴ (A+B+C) can do the work in =`24/7` days
`=3 3/7` days
APPEARS IN
RELATED QUESTIONS
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?