Question
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
Advertisements
Solution
A can do a piece of work in = 6 days
B can do a piece of work in = 12 days
C can do a piece of work in = 24 days
∴ A's 1-day work =`1/6`
∴ B's 1-day work = `1/12`
∴ C's 1-day work = `1/24`
(A+B+C)'s 1-day work =`1/6+1/12+1/24`
`=(4+2+1)/24=7/24`
∴ (A+B+C) can do the work in =`24/7` days
`=3 3/7` days
APPEARS IN
RELATED QUESTIONS
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?