Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?

Advertisements
Advertisements

प्रश्न

Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?

बेरीज
Advertisements

उत्तर

Amutha can weave a saree in 18 days.

Anjali is twice as good as Amutha.

ie. If Amutha weave for 2 days, Anjali do the same work in 1 day.

If Anjali weave the saree she will take

`18/2` = 9 days

Hence time taken by them together ab

= `"ab"/("a" + "b")` days

= `(18 xx 9)/(18 + 9)`

= `(18 xx 9)/27`

= `(6 xx 1)/3`

= 6 days

In 6 days they complete weaving the saree.

shaalaa.com
Compound Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 4: Life Mathematics - Exercise 4.5 [पृष्ठ १५१]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
पाठ 4 Life Mathematics
Exercise 4.5 | Q 7 | पृष्ठ १५१

संबंधित प्रश्‍न

If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days


A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days


A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________


210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together


A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


If the numerator of a fraction is increased by 50% and the denominator is decreased by 20%, then it becomes `3/5`. Find the original fraction


A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×