Let the required number of men be x.

Hours Day Men
12 18 210
14 20 x

More working hours ⇒ less men required.

∴ It is inverse proportion.

∴ Multiplying factor is `12/14`

Also more number of days ⇒ less men

∴ It is an inverse proportion

∴ Multiplying factor is `18/20`

∴ x = `210 xx 12/14 xx 18/20`

`(210 xx 12 xx 18)/(14 xx 20)`

 x = 162 men

162 men are required.

shaalaa.com
Compound Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 4: Life Mathematics - Exercise 4.4 [पृष्ठ १५०]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
पाठ 4 Life Mathematics
Exercise 4.4 | Q 2 | पृष्ठ १५०

संबंधित प्रश्‍न

A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days


A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days


A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________


A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?


If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×