A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines? - Mathematics

Advertisements
Advertisements

प्रश्न

A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?

बेरीज
Advertisements

उत्तर

Let he required number of cement bags be x.

Days Machines Cement bags
12 36 7000
18 24 x

Number of days more ⇒ More cement bags.

∴ It is direct variation.

∴ The multiplying factor = `18/12`

Number of machines more ⇒ More cement bags.

∴ It is direct variation.

∴ The multiplying factor =`24/36`

∴ x = `7000 xx 18/12 xx 24/36`

`(7000 xx 18 xx 24)/(12 xx 36)`

x = 7000 cement bags

7000 cement bags can be made

shaalaa.com
Compound Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 4: Life Mathematics - Exercise 4.4 [पृष्ठ १५०]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
पाठ 4 Life Mathematics
Exercise 4.4 | Q 3 | पृष्ठ १५०

संबंधित प्रश्‍न

A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days


A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________


210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?


A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?


If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×