प्रश्न
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?
Advertisements
उत्तर
| Days (D) | Hours (H) | Men (P) |
| 15 | 12 | 32 |
| 25 | 10 | x |
Let
P1 = 32
P2 = x
H1 = 12
H2 = 10
D1 = 15
D2 = 24
W1 = 1
W2 = 1
Using formula, `("P"_1 xx "D"_1 xx "H"_1)/("W"_1)` = `("P"_2 xx "D"_2 xx "H"_2)/("W"_2)`
= `(32 xx 15 xx 12)/1` = `(x xx 24 xx 10)/1`
x = `(35 xx 15 xx 12)/(24 xx 10)`
x = `(8 xx 3 xx1)/(1 xx 1)`
x = 24 persons
To complete the same work 24 men needed.
To complete double the work 24 × 2 = 48 men are required.
APPEARS IN
संबंधित प्रश्न
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days
A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________
210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?
A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?
If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?
A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together