A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?
Advertisements
उत्तर
Let the number of men to be appointed more be x.
| Motor pumps | Days | Employees | |
| Planned | 540 | 150 | 40 |
| Produced | 180 | 75 | 40 |
| Remaining | 360 | 75 | 40 + x |
To produce more pumps more men required
∴ It is direct variation.
∴ The multiplying factor is `360/180`
More days means less employees needed.
∴ It is Indirect proportion 75
∴ The multiplying factor is `75/75`
Now 40 + x = `40 xx 360/180 xx 75/75`
40 + x = 80
x = 80 – 40
x = 40
40 more man should be employed to complete the work on time as per the agreement.
APPEARS IN
संबंधित प्रश्न
A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days
If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days
210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?
A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?
If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?
A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?
A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?
Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?