A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together

बेरीज
Advertisements

उत्तर

A complete the work in 45 days.

∴ A’s 1 day work = `1/45`

A's 15 days work = `15/45 = 1/3`

Remaining work = `1 - 1/3 = (3 - 1)/3 = 2/3`

B finishes `2/3` rd work in 24 days

B's 1 day work = `(2/3)/24`

= `2/(3 xx 24)`

= `1/36`

(A + B)'s 1 day work = `1/45 + 1/36`

9 45, 36
5, 4

= `(4 + 5)/180`

= `9/180`

= `1/20`

Let x days required

∴ `x/20 = 80/100`

⇒ x = `80/100 xx 20`

= 16 days

shaalaa.com
Compound Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 4: Life Mathematics - Exercise 4.4 [पृष्ठ १५१]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
पाठ 4 Life Mathematics
Exercise 4.4 | Q 9 | पृष्ठ १५१
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×