Advertisements
Advertisements
प्रश्न
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
Advertisements
उत्तर
Time taken by A to complete the work = 12 hours.
∴ A’s 1 hour work = `1/12` ...(1)
(B + C) complete the work in 3 hours.
∴ (B + C)’s 1 hour work = `1/3` ...(2)
Add (1) and (2)
∴ (A + B + C)’s 1 hour work = `1/12 + 1/3`
= `(1 + 4)/12`
= `5/12`
Now (A + C) complete the work in 6 hours.
∴(A + C)’s 1 hour work = `1/6`
∴ B’s 1 hour work = (A + B + C)’s 1 hour work – (A + C)’s 1 hour work
= `5/12 - 1/6`
= `(5 - 2)/12`
= `3/12`
= `1/4`
∴ B alone take 4 days to complete the work.
APPEARS IN
संबंधित प्रश्न
If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________
A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?
A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?
A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?
A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together
Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?
If the numerator of a fraction is increased by 50% and the denominator is decreased by 20%, then it becomes `3/5`. Find the original fraction
A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?
