If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?

Advertisements
Advertisements

प्रश्न

If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?

बेरीज
Advertisements

उत्तर

Let the number of lorries required more = x.

Container lorries Goods (tonnes) Days
6 135 5
6 + x 180 4

As the goods are more ⇒ More lorries are needed to transport.

∴ It is direct proportion.

∴ Multiplying factor = `180/135`

Again if more days ⇒ less number of lorries enough.

∴ It is direct proportion.

∴ Multiplying factor = `5/4`

∴ 6 + x = `6 xx 180/135 xx 5/4`

`6 xx 180/135 xx 5/4`

6 + x = 10

x = 10 – 6

x = 4

∴ 4 more lorries are required.

shaalaa.com
Compound Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 4: Life Mathematics - Exercise 4.4 [पृष्ठ १५०]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
पाठ 4 Life Mathematics
Exercise 4.4 | Q 5 | पृष्ठ १५०

संबंधित प्रश्‍न

A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days


If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days


A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days


A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________


A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together


A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×