प्रश्न
If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?
Advertisements
उत्तर
Let the number of lorries required more = x.
| Container lorries | Goods (tonnes) | Days |
| 6 | 135 | 5 |
| 6 + x | 180 | 4 |
As the goods are more ⇒ More lorries are needed to transport.
∴ It is direct proportion.
∴ Multiplying factor = `180/135`
Again if more days ⇒ less number of lorries enough.
∴ It is direct proportion.
∴ Multiplying factor = `5/4`
∴ 6 + x = `6 xx 180/135 xx 5/4`
`6 xx 180/135 xx 5/4`
6 + x = 10
x = 10 – 6
x = 4
∴ 4 more lorries are required.
APPEARS IN
संबंधित प्रश्न
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?
A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?
Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?
If the numerator of a fraction is increased by 50% and the denominator is decreased by 20%, then it becomes `3/5`. Find the original fraction
A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?