A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together - Mathematics

Advertisements
Advertisements

Question

A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together

Sum
Advertisements

Solution

A complete the work in 45 days.

∴ A’s 1 day work = `1/45`

A's 15 days work = `15/45 = 1/3`

Remaining work = `1 - 1/3 = (3 - 1)/3 = 2/3`

B finishes `2/3` rd work in 24 days

B's 1 day work = `(2/3)/24`

= `2/(3 xx 24)`

= `1/36`

(A + B)'s 1 day work = `1/45 + 1/36`

9 45, 36
5, 4

= `(4 + 5)/180`

= `9/180`

= `1/20`

Let x days required

∴ `x/20 = 80/100`

⇒ x = `80/100 xx 20`

= 16 days

shaalaa.com
Compound Variation
  Is there an error in this question or solution?
Chapter 4: Life Mathematics - Exercise 4.4 [Page 151]

APPEARS IN

Samacheer Kalvi Mathematics [English] Class 8 TN Board
Chapter 4 Life Mathematics
Exercise 4.4 | Q 9 | Page 151

RELATED QUESTIONS

A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days


If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days


A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days


A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?


If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together


A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×