A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?

Advertisements
Advertisements

Question

A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?

Sum
Advertisements

Solution

(A + B) complete the work in 12 days.

∴ (A + B)’s 1 day work = `1/12`  ...(1)

(B + C) complete the work in 15 days

∴ (B + C)’s 1 day work = `1/15`  ...(2)

(A + C) complete the work in 20 days

∴ (A + C)’s 1 day work = `1/20`  ...(3)

Now (1) + (2) + (3) =

[(A + B) + (B + C) + (A + C)]’s 1 day work = `1/12 + 1/15 + 1/20`

(2A + 2B + 2C)’s 1 day work = `5/60 + 4/60 + 3/60`

2(A + B + C)’s 1 day work = `(5 + 4 + 3)/60`

5 12, 15, 20
4 12, 3, 4
3 3, 3, 1
  1, 1, 1

L.C.M = 5 × 4 × 3 = 60

(A + B + C)’s 1 day work = `12/(60 xx 2)`

(A + B + C)’s 1 day work = `1/10`

Now A’s 1 day’s work = (A + B + C)’s 1 day work – (B + C)’s 1 day work

= `1/10 - 1/15`

= `3/30 - 2/30`

= `1/30`

∴ A takes 30 days to complete the work.

B’s 1 day work – (A + B + C)’s 1 day’s work – (A + C)’s 1 day’s work

= `1/10 - 1/20`

= `6/60 - 3/60`

= `(6 - 3)/60`

= `3/60`

= `1/20`

B takes 20 days to complete the work.

C’s 1 day work (A + B + C)’s 1 day work – (A + B)’s 1 day work

= `1/10 - 1/12`

= `6/60 - 5/60`

= `(6 - 5)/60`

= `1/60`

∴ C takes 60 days to complete the work.

shaalaa.com
Compound Variation
  Is there an error in this question or solution?
Chapter 4: Life Mathematics - Exercise 4.4 [Page 150]

APPEARS IN

Samacheer Kalvi Mathematics [English] Class 8 TN Board
Chapter 4 Life Mathematics
Exercise 4.4 | Q 7 | Page 150

RELATED QUESTIONS

If 5 persons can do 5 jobs in 5 days, then 50 persons can do 50 jobs in _________ days


A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days


A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?


If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?


If the numerator of a fraction is increased by 50% and the denominator is decreased by 20%, then it becomes `3/5`. Find the original fraction


A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×