प्रश्न
50 labourers can dig a pond in 16 days. How many labourers will be required to dig another pond, double in size in 20 days?
Advertisements
उत्तर
In 16 days for diging pond labour reqd.
In 1 day, labour reqd. = 50 × 16
In 20 days, labour reqd. = `(50xx16)/20`
In 20 days, with double work, labour reqd.
`=(50xx16xx2)/20`
= 5 × 8 × 2
= 80
Hence labourers required = 80
APPEARS IN
संबंधित प्रश्न
`3/5` quintal of wheat costs Rs.210. Find the cost of :
(i) 1 quintal of wheat
(ii) 0.4 quintal of wheat
If `2/9` of property costs Rs.2,52,000; find the cost of `4/7` of it.
If 25 horses consume 18 quintal in 36 days, how long will 28 quintal last for 30 horses?
Ten men, working for 6 days of 10 hours each, finish `5/21` of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days?
If the cost of a dozen soaps is ₹ 460.80, what will the cost of 15 soaps?
The cost of 35 envelops is ₹ 105. How many envelops can be bought for ₹ 90?
For ₹ 378, 9 cans of juice can be bought, then how many cans of juice can be bought for ₹ 504?
Cost of 10 kg of wheat is ₹ 180. What is the cost of 18 kg of wheat?
Geeta types 108 words in 6 minutes. How many words would she type in half an hour?
Mr. Chopra pays ₹ 12,000 as rent for 3 months. How much does he has to pay for a year if the rent per month remains same?