प्रश्न
If 70 men dig 15,000 sq. m of a field in 5 days, how many men will dig 22,500 sq. m field in 25 days?
Advertisements
उत्तर
70 men dig 15,000 sq. m of a field in 5 days
1 man can dig 15,000 sq. m of a field in =`(5xx70)/ (15,000)`
Men required to dig 22,500 sq. m. a field in 25 days
`=(5xx70xx22500)/(15,000xx25)=(70xx900)/3000=63/3=21`
Hence required to dig 22,500 sq. m field in 25 days = 21
APPEARS IN
संबंधित प्रश्न
16 boys went to the canteen to have tea and snacks together. The bill amounted to Rs. 114.40. What will be the contribution of a boy who pays for himself and 5 others?
Eight oranges can be bought for Rs. 10.40. How many more can be bought for Rs.16.90?
Ten men, working for 6 days of 10 hours each, finish `5/21` of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days?
If the cost of a dozen soaps is ₹ 460.80, what will the cost of 3 dozen soaps?
Cost of 10 kg of wheat is ₹ 180. What is the cost of 18 kg of wheat?
A tree 24 m high casts a shadow of 15 m. At the same time, the length of the shadow casted by some other tree is 6 m. Find the height of the tree.
A made 84 runs in 6 overs and B made 126 runs in 7 overs. Who made more runs per over?
25 metres of cloth costs ₹ 1,012.50. What will be the cost of 20 metres of cloth of the same type?
In the unitary method, which mathematical operation is used to convert the value of "many" units to the value of "one" unit?
30 identical articles weigh 360 g. How many articles will weigh 840 g?