If 70 men dig 15,000 sq. m of a field in 5 days, how many men will dig 22,500 sq. m field in 25 days?
Advertisements
उत्तर
70 men dig 15,000 sq. m of a field in 5 days
1 man can dig 15,000 sq. m of a field in =`(5xx70)/ (15,000)`
Men required to dig 22,500 sq. m. a field in 25 days
`=(5xx70xx22500)/(15,000xx25)=(70xx900)/3000=63/3=21`
Hence required to dig 22,500 sq. m field in 25 days = 21
APPEARS IN
संबंधित प्रश्न
If `2/9` of property costs Rs.2,52,000; find the cost of `4/7` of it.
One tap can fill a cistern in 3 hours and the waste pipe can empty the full cistern in 5 hours. In what time will the empty cistern be full, if the tap and the waste pipe are kept open together?
The price of 25 identical articles is ₹1,750. Find the price of 13 articles
A motorbike travels 330 km in 5 litres of petrol. How much distance will it cover in one litre of petrol?
For ₹ 378, 9 cans of juice can be bought, then how many cans of juice can be bought for ₹ 504?
A motorbike travels 425 km in 5 hours. How much distance will be covered by it in 3.2 hours?
Cost of 10 kg of wheat is ₹ 180. What quantity of wheat can be purchased in ₹ 432?
A tree 24 m high casts a shadow of 15 m. At the same time, the length of the shadow casted by some other tree is 6 m. Find the height of the tree.
If John walks 250 steps to cover a distance of 200 metres, find the distance covered by him in 350 steps
In a particular week, a man works for 48 hours and earns ₹ 4,320. But in the next week he worked 6 hours less, how much has he earned in this week?