Question
If 70 men dig 15,000 sq. m of a field in 5 days, how many men will dig 22,500 sq. m field in 25 days?
Advertisements
Solution
70 men dig 15,000 sq. m of a field in 5 days
1 man can dig 15,000 sq. m of a field in =`(5xx70)/ (15,000)`
Men required to dig 22,500 sq. m. a field in 25 days
`=(5xx70xx22500)/(15,000xx25)=(70xx900)/3000=63/3=21`
Hence required to dig 22,500 sq. m field in 25 days = 21
APPEARS IN
RELATED QUESTIONS
If `2/9` of property costs Rs.2,52,000; find the cost of `4/7` of it.
4 men or 6 women earn Rs. 360 in one day. Find, how much will:
(i) a man earn in one day?
(ii) a woman earn in one day?
(iii) 6 men and 4 women earn in one day?
A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?
For ₹ 378, 9 cans of juice can be bought, then how many cans of juice can be bought for ₹ 504?
A motorbike travels 425 km in 5 hours. How much distance will be covered by it in 3.2 hours?
A car covers a distance of 180 km in 5 hours. How much time will the car take to cover 54 km with the same speed?
If it has rained 276 cm in the last 3 days, how many cm of rain will fall in one week (7 days)?
Assume that the rain continues to fall at the same rate.
A loaded truck travels 18 km in 25 minutes. If the speed remains the same, how far can it travel in 5 hours?
If a deposit of ₹ 2,000 earns an interest of ₹ 500 in 3 years, how much interest would a deposit of ₹ 36,000 earn in 3 years with the same rate of simple interest?
What is the primary objective of the "Unitary Method"?