प्रश्न
A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?
Advertisements
उत्तर
Number of men employed in the beginning = 56
Length of wall = 1000 m No. of days = 50
In the time of 27 days, only 448 m of the wall was completed
Remaining period = 50 – 27 = 23 days
and length of wall to be completed = 1000 – 448 = 552
Now in 27 days, 448 m long wall was completed by = 1000 m
in 1 day, 448 m long was completed by = 56 x 27
in 1 day, 1 m long wall will be completed by
`=(56xx27)/448` m
and in 23 days 552 m long wall be completed by
`=(56xx27xx552)/(448xx23)` men
`=(1xx27xx24)/8` = 81 men
∴ No. of extra men required
= 81 − 56 = 25 men
APPEARS IN
संबंधित प्रश्न
A particular work can be completed by 6 men and 6 women in 24 days; whereas the same work can be completed by 8 men and 12 women in 15 days. Find :
(i) according to the amount of work done, one man is equivalent to how many women.
(ii) the time is taken by 4 men and 6 women to complete the same work.
Eight oranges can be bought for Rs. 10.40. How many more can be bought for Rs.16.90?
Fifteen men can build a wall in 60 days. How many more men are required to build another wall of the same size in 45 days?
If 25 horses consume 18 quintal in 36 days, how long will 28 quintal last for 30 horses?
If 70 men dig 15,000 sq. m of a field in 5 days, how many men will dig 22,500 sq. m field in 25 days?
If the cost of a dozen soaps is ₹ 460.80, what will the cost of each soap?
The cost of 35 envelops is ₹ 105. How many envelops can be bought for ₹ 90?
If the cost of 8 cans of juice is ₹ 280, then what will be the cost of 6 cans of juice?
Mr. Chopra pays ₹ 12,000 as rent for 3 months. How much does he has to pay for a year if the rent per month remains same?
If John walks 250 steps to cover a distance of 200 metres, find the distance covered by him in 350 steps