प्रश्न
A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?
Advertisements
उत्तर
Number of men employed in the beginning = 56
Length of wall = 1000 m No. of days = 50
In the time of 27 days, only 448 m of the wall was completed
Remaining period = 50 – 27 = 23 days
and length of wall to be completed = 1000 – 448 = 552
Now in 27 days, 448 m long wall was completed by = 1000 m
in 1 day, 448 m long was completed by = 56 x 27
in 1 day, 1 m long wall will be completed by
`=(56xx27)/448` m
and in 23 days 552 m long wall be completed by
`=(56xx27xx552)/(448xx23)` men
`=(1xx27xx24)/8` = 81 men
∴ No. of extra men required
= 81 − 56 = 25 men
APPEARS IN
संबंधित प्रश्न
One tap can fill a cistern in 3 hours and the waste pipe can empty the full cistern in 5 hours. In what time will the empty cistern be full, if the tap and the waste pipe are kept open together?
If the cost of 8 cans of juice is ₹ 280, then what will be the cost of 6 cans of juice?
A motorbike travels 425 km in 5 hours. How much distance will be covered by it in 3.2 hours?
If the cost of a dozen identical articles is ₹ 672, what will be the cost of 18 such articles?
A tree 24 m high casts a shadow of 15 m. At the same time, the length of the shadow casted by some other tree is 6 m. Find the height of the tree.
Weight of 15 books is 6 kg. What is the weight of 45 such books?
A made 84 runs in 6 overs and B made 126 runs in 7 overs. Who made more runs per over?
Mr. Chopra pays ₹ 12,000 as rent for 3 months. How much does he has to pay for a year if the rent per month remains same?
25 metres of cloth costs ₹ 1,012.50. What will be the cost of 20 metres of cloth of the same type?
Once the value of a single unit is known, which operation is used to find the value of "many" units?