A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?
Advertisements
उत्तर
Number of men employed in the beginning = 56
Length of wall = 1000 m No. of days = 50
In the time of 27 days, only 448 m of the wall was completed
Remaining period = 50 – 27 = 23 days
and length of wall to be completed = 1000 – 448 = 552
Now in 27 days, 448 m long wall was completed by = 1000 m
in 1 day, 448 m long was completed by = 56 x 27
in 1 day, 1 m long wall will be completed by
`=(56xx27)/448` m
and in 23 days 552 m long wall be completed by
`=(56xx27xx552)/(448xx23)` men
`=(1xx27xx24)/8` = 81 men
∴ No. of extra men required
= 81 − 56 = 25 men
APPEARS IN
संबंधित प्रश्न
The price of 25 identical articles is ₹1,750. Find the price of 13 articles
If the cost of a dozen soaps is ₹ 460.80, what will the cost of each soap?
For ₹ 378, 9 cans of juice can be bought, then how many cans of juice can be bought for ₹ 504?
A motorbike travels 425 km in 5 hours. How much distance will be covered by it in 3.2 hours?
A car covers a distance of 180 km in 5 hours. How much time will the car take to cover 54 km with the same speed?
Weight of 15 books is 6 kg. What is the weight of 45 such books?
Geeta types 108 words in 6 minutes. How many words would she type in half an hour?
The temperature dropped 18 degree Celsius in the last 24 days. If the rate of temperature drop remains the same, how many degrees will the temperature drop in the next 18 days?
A truck requires 108 litres of diesel for covering a distance of 1188 km. How much diesel will be required by the truck to cover a distance of 3300 km?
If a deposit of ₹ 2,000 earns an interest of ₹ 500 in 3 years, how much interest would a deposit of ₹ 36,000 earn in 3 years with the same rate of simple interest?