प्रश्न
A contractor undertakes to build a wall 1000 m long in 50 days. He employs 56 men, but at the end of 27 days, he finds that only 448 m of wall is built. How many extra men must the contractor employ so that the wall is completed in time?
Advertisements
उत्तर
Number of men employed in the beginning = 56
Length of wall = 1000 m No. of days = 50
In the time of 27 days, only 448 m of the wall was completed
Remaining period = 50 – 27 = 23 days
and length of wall to be completed = 1000 – 448 = 552
Now in 27 days, 448 m long wall was completed by = 1000 m
in 1 day, 448 m long was completed by = 56 x 27
in 1 day, 1 m long wall will be completed by
`=(56xx27)/448` m
and in 23 days 552 m long wall be completed by
`=(56xx27xx552)/(448xx23)` men
`=(1xx27xx24)/8` = 81 men
∴ No. of extra men required
= 81 − 56 = 25 men
APPEARS IN
संबंधित प्रश्न
16 boys went to the canteen to have tea and snacks together. The bill amounted to Rs. 114.40. What will be the contribution of a boy who pays for himself and 5 others?
Eight oranges can be bought for Rs. 10.40. How many more can be bought for Rs.16.90?
If 10 horses consume 18 bushels in 36 days. How long will 24 bushels last for 30 horses?
The price of 25 identical articles is ₹1,750. Find the price of one article
The cost of 35 envelops is ₹ 105. How many envelops can be bought for ₹ 90?
If the cost of 8 cans of juice is ₹ 280, then what will be the cost of 6 cans of juice?
A motorbike travels 425 km in 5 hours. How much distance will be covered by it in 3.2 hours?
A car covers a distance of 180 km in 5 hours. How much distance will the car cover in 3 hours with the same speed?
The temperature dropped 18 degree Celsius in the last 24 days. If the rate of temperature drop remains the same, how many degrees will the temperature drop in the next 18 days?
A truck requires 108 litres of diesel for covering a distance of 1188 km. How much diesel will be required by the truck to cover a distance of 3300 km?