Question

In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?

Sum
Advertisements

Solution 1

After 10 days:

For 150 men, provision will last (45 − 10)

days = 35 days

⇒ For 1 man, the provisions will last

= 150 × 35 days

And for (150 − 25) = 125 men, the provisions

will last for =`(150xx35)/125`

= 42 days

shaalaa.com

Solution 2

Given: 

  1. 150 men have food for 45 days.
  2. After 10 days, 25 men leave the fort.
  3. We need to find how long the remaining food will last for 125 men.

The total amount of food is:

Total food = 150⋅45 = 6750 man-days.

Food consumed by 150 men in 10 days is

Food consumed = 150⋅10 = 1500 man-days.

The remaining food after 10 days is

Remaining food = 6750 − 1500 = 5250 man-days.

After 25 men leave, the remaining men are:

Remaining men = 150 − 25 = 125.

The number of days the remaining food will last for 125 men is:

Remaining days = `"Remaining food"/"Remaining men"=5250/125`

= 42 days

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10 (B) [Page 123]

APPEARS IN

Selina Concise Mathematics [English] Class 8 ICSE
Chapter 10 Direct and Inverse Variations
Exercise 10 (B) | Q 5 | Page 123

RELATED QUESTIONS

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×