Advertisements
Advertisements
Question
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Advertisements
Solution

E1 = 0
E2 = 0 + 5 = 5
E3 = (5 + 3) or (0 + 10)
Whichever is maximum
= 10
E4 = 10 + 4 = 14
E5 = 10 + 6 = 16
E6 = (14 + 6) or (16 + 5)
Whichever is maximum
= 21
E7 = 21 + 5 = 26
L7 = 26
L6 = 26 − 5 = 21
L5 = 21 − 5 = 16
L4 = 21 − 6 = 15
L3 = (15 − 4) or (16 − 6)
Whichever is minimum
= 10
L2 = 10 − 3 = 7
L1 = (7 − 5) or (10 − 10)
Whichever is minimum
L1 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 5 | 0 | 5 | 7 − 5 = 2 | 7 |
| 1 - 3 | 10 | 0 | 10 | 10 − 10 = 0 | 10 |
| 2 - 3 | 3 | 5 | 8 | 10 − 3 = 7 | 10 |
| 3 - 4 | 4 | 10 | 14 | 15 − 4 = 11 | 15 |
| 3 - 5 | 6 | 10 | 16 | 16 − 6 = 10 | 16 |
| 4 - 6 | 6 | 14 | 20 | 21 − 6 = 15 | 21 |
| 5 - 6 | 5 | 16 | 21 | 21 − 5 = 16 | 21 |
| 6 - 7 | 5 | 21 | 26 | 26 − 5 = 21 | 26 |
Since EFT and LFT values are same in 1 - 3, 3 - 5, 5 - 6 and 6 - 7.
Hence the critical path is 1 - 3 - 5 - 6 - 7 and the duration of time taken is 26 days.
APPEARS IN
RELATED QUESTIONS
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
In the context of network, which of the following is not correct
The objective of network analysis is to
Network problems have the advantage in terms of project
Draw a network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G | H | I | J | K |
| Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
