English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

A Project has the following time schedule Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6 Duration(in days) 6 8 4 9 2 7

Advertisements
Advertisements

Question

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

Sum
Advertisements

Solution

E1 = 0

E2 = 0 + 6 = 6

E3 = 6 + 8 = 14

E4 = 6 + 4 = 10

E5 = 14 + 9 = 23

E6 = (23 + 7) or (10 + 2)

Whichever is maximum

= 30

L6 = 30

L5 = 30 − 6 = 24

L4 = 30 − 2 = 28

L3 = 23 − 9 = 14

L2 = (14 − 8) or (28 − 4)

Whichever is minimum

= 6

L1 = 6 − 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 − 6 = 0 6
2 - 3 8 6 14 14 − 8 = 6 14
2 - 4 4 6 10 28 − 4 = 24 28
3 - 5 9 14 23 23 − 9 = 14 23
4 - 6 2 10 22 30 − 28 = 2 4
5 - 6 7 23 30 30 − 7 = 23 30

Since EFT and LFT values are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 6.

Hence the critical path is 1 - 2 - 3 - 5 - 6 and the duration of time taken is 30 days.

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Miscellaneous Problems [Page 252]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Miscellaneous Problems | Q 9 | Page 252

RELATED QUESTIONS

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


Which of the following is not correct?


The objective of network analysis is to


Network problems have the advantage in terms of project


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×