Advertisements
Advertisements
Question
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
Advertisements
Solution

E1 = 0 + 3 = 3
E2 = E1 + t12 = 8 + 3 = 11
E3 = 3 + 12 = 15
E4 = 15 + 3 = 18
E5 = E2 + 3 = 11 + 3 = 14
E6 = E3 + 8 = 15 + 8 = 23
E7 = E6 + 8 = 23 + 8 = 31
L7 = 31
L6 = L7 – 8 = 31 – 8 = 23
L5 = L7 – 3 = 31 – 3 = 28
L4 = L7 – 5 = 31 – 5 = 26
L3 = L6 – 8 = 23 – 8 = 15
L2 = L5 – 3 or L4 which is minimum
= (28 – 3) or (26 – 6)
= 25 or 20
= 20 (which is minimum)
L1 = L2 – 8 or L3 – 12
whichever is minimum
= (20 – 8) or (15 – 12)
= 12 or 3
= 3
L0 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 0 - 1 | 3 | 0 | 3 | 3 | 3 |
| 1 - 2 | 8 | 3 | 11 | 20 – 8 = 12 | 20 |
| 1 - 3 | 12 | 3 | 15 | 15 – 12 = 3 | 15 |
| 2 - 4 | 6 | 11 | 17 | 26 – 6= 20 | 26 |
| 2 - 5 | 3 | 11 | 14 | 28 – 3 = 25 | 28 |
| 3 - 4 | 3 | 15 | 18 | 26 – 3 = 23 | 26 |
| 3 - 6 | 8 | 15 | 23 | 23 – 8 = 15 | 23 |
| 4 - 7 | 5 | 18 | 23 | 31 – 5 = 26 | 31 |
| 5 - 7 | 3 | 14 | 14 | 31 – 3 = 28 | 31 |
| 6 - 7 | 8 | 23 | 31 | 31 – 8 = 23 | 31 |
The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.
APPEARS IN
RELATED QUESTIONS
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
| Activity | A | B | C | D | E | F | G | H | I | J | K |
| Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The critical path of the following network is

One of the conditions for the activity (i, j) to lie on the critical path is
Which of the following is not correct?
In the context of network, which of the following is not correct
Draw a network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G | H | I | J | K |
| Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
