Advertisements
Advertisements
Question
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
Advertisements
Solution

E1 = 0 + 3 = 3
E2 = E1 + t12 = 8 + 3 = 11
E3 = 3 + 12 = 15
E4 = 15 + 3 = 18
E5 = E2 + 3 = 11 + 3 = 14
E6 = E3 + 8 = 15 + 8 = 23
E7 = E6 + 8 = 23 + 8 = 31
L7 = 31
L6 = L7 – 8 = 31 – 8 = 23
L5 = L7 – 3 = 31 – 3 = 28
L4 = L7 – 5 = 31 – 5 = 26
L3 = L6 – 8 = 23 – 8 = 15
L2 = L5 – 3 or L4 which is minimum
= (28 – 3) or (26 – 6)
= 25 or 20
= 20 (which is minimum)
L1 = L2 – 8 or L3 – 12
whichever is minimum
= (20 – 8) or (15 – 12)
= 12 or 3
= 3
L0 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 0 - 1 | 3 | 0 | 3 | 3 | 3 |
| 1 - 2 | 8 | 3 | 11 | 20 – 8 = 12 | 20 |
| 1 - 3 | 12 | 3 | 15 | 15 – 12 = 3 | 15 |
| 2 - 4 | 6 | 11 | 17 | 26 – 6= 20 | 26 |
| 2 - 5 | 3 | 11 | 14 | 28 – 3 = 25 | 28 |
| 3 - 4 | 3 | 15 | 18 | 26 – 3 = 23 | 26 |
| 3 - 6 | 8 | 15 | 23 | 23 – 8 = 15 | 23 |
| 4 - 7 | 5 | 18 | 23 | 31 – 5 = 26 | 31 |
| 5 - 7 | 3 | 14 | 14 | 31 – 3 = 28 | 31 |
| 6 - 7 | 8 | 23 | 31 | 31 – 8 = 23 | 31 |
The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.
APPEARS IN
RELATED QUESTIONS
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
| Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
In constructing the network which one of the following statements is false?
Network problems have the advantage in terms of project
Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
A Project has the following time schedule
| Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
| Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
