मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

Construct the network for the project whose activities are given below. Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7 Duration (in week) 3 8 12 6 3 3 8 5 3 8

Advertisements
Advertisements

प्रश्न

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.

बेरीज
Advertisements

उत्तर

E1 = 0 + 3 = 3

E2 = E1 + t12 = 8 + 3 = 11

E3 = 3 + 12 = 15

E4 = 15 + 3 = 18

E5 = E2 + 3 = 11 + 3 = 14

E6 = E3 + 8 = 15 + 8 = 23

E7 = E6 + 8 = 23 + 8 = 31

L7 = 31

L6 = L7 – 8 = 31 – 8 = 23

L5 = L7 – 3 = 31 – 3 = 28

L4 = L7 – 5 = 31 – 5 = 26

L3 = L6 – 8 = 23 – 8 = 15

L2 = L5 – 3 or L4 which is minimum

= (28 – 3) or (26 – 6)

= 25 or 20

= 20 (which is minimum)

L1 = L2 – 8 or L3 – 12

whichever is minimum

= (20 – 8) or (15 – 12)

= 12 or 3

= 3

L0 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
0 - 1 3 0 3 3 3
1 - 2 8 3 11 20 – 8 = 12 20
1 - 3 12 3 15 15 – 12 = 3 15
2 - 4 6 11 17 26 – 6= 20 26
2 - 5 3 11 14 28 – 3 = 25 28
3 - 4 3 15 18 26 – 3 = 23 26
3 - 6 8 15 23 23 – 8 = 15 23
4 - 7 5 18 23 31 – 5 = 26 31
5 - 7 3 14 14 31 – 3 = 28 31
6 - 7 8 23 31 31 – 8 = 23 31

The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 5 | पृष्ठ २४९

संबंधित प्रश्‍न

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


Which of the following is not correct?


In the context of network, which of the following is not correct


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×