Advertisements
Advertisements
प्रश्न
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
Advertisements
उत्तर

E1 = 0 + 3 = 3
E2 = E1 + t12 = 8 + 3 = 11
E3 = 3 + 12 = 15
E4 = 15 + 3 = 18
E5 = E2 + 3 = 11 + 3 = 14
E6 = E3 + 8 = 15 + 8 = 23
E7 = E6 + 8 = 23 + 8 = 31
L7 = 31
L6 = L7 – 8 = 31 – 8 = 23
L5 = L7 – 3 = 31 – 3 = 28
L4 = L7 – 5 = 31 – 5 = 26
L3 = L6 – 8 = 23 – 8 = 15
L2 = L5 – 3 or L4 which is minimum
= (28 – 3) or (26 – 6)
= 25 or 20
= 20 (which is minimum)
L1 = L2 – 8 or L3 – 12
whichever is minimum
= (20 – 8) or (15 – 12)
= 12 or 3
= 3
L0 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 0 - 1 | 3 | 0 | 3 | 3 | 3 |
| 1 - 2 | 8 | 3 | 11 | 20 – 8 = 12 | 20 |
| 1 - 3 | 12 | 3 | 15 | 15 – 12 = 3 | 15 |
| 2 - 4 | 6 | 11 | 17 | 26 – 6= 20 | 26 |
| 2 - 5 | 3 | 11 | 14 | 28 – 3 = 25 | 28 |
| 3 - 4 | 3 | 15 | 18 | 26 – 3 = 23 | 26 |
| 3 - 6 | 8 | 15 | 23 | 23 – 8 = 15 | 23 |
| 4 - 7 | 5 | 18 | 23 | 31 – 5 = 26 | 31 |
| 5 - 7 | 3 | 14 | 14 | 31 – 3 = 28 | 31 |
| 6 - 7 | 8 | 23 | 31 | 31 – 8 = 23 | 31 |
The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.
APPEARS IN
संबंधित प्रश्न
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
| Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
The critical path of the following network is

In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
In the context of network, which of the following is not correct
Network problems have the advantage in terms of project
Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
