मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

Construct the network for the project whose activities are given below. Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7 Duration (in week) 3 8 12 6 3 3 8 5 3 8 - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.

बेरीज
Advertisements

उत्तर

E1 = 0 + 3 = 3

E2 = E1 + t12 = 8 + 3 = 11

E3 = 3 + 12 = 15

E4 = 15 + 3 = 18

E5 = E2 + 3 = 11 + 3 = 14

E6 = E3 + 8 = 15 + 8 = 23

E7 = E6 + 8 = 23 + 8 = 31

L7 = 31

L6 = L7 – 8 = 31 – 8 = 23

L5 = L7 – 3 = 31 – 3 = 28

L4 = L7 – 5 = 31 – 5 = 26

L3 = L6 – 8 = 23 – 8 = 15

L2 = L5 – 3 or L4 which is minimum

= (28 – 3) or (26 – 6)

= 25 or 20

= 20 (which is minimum)

L1 = L2 – 8 or L3 – 12

whichever is minimum

= (20 – 8) or (15 – 12)

= 12 or 3

= 3

L0 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
0 - 1 3 0 3 3 3
1 - 2 8 3 11 20 – 8 = 12 20
1 - 3 12 3 15 15 – 12 = 3 15
2 - 4 6 11 17 26 – 6= 20 26
2 - 5 3 11 14 28 – 3 = 25 28
3 - 4 3 15 18 26 – 3 = 23 26
3 - 6 8 15 23 23 – 8 = 15 23
4 - 7 5 18 23 31 – 5 = 26 31
5 - 7 3 14 14 31 – 3 = 28 31
6 - 7 8 23 31 31 – 8 = 23 31

The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 5 | पृष्ठ २४९

संबंधित प्रश्‍न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The critical path of the following network is


In constructing the network which one of the following statements is false?


In a network while numbering the events which one of the following statements is false?


In the context of network, which of the following is not correct


Network problems have the advantage in terms of project


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×