मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

In a network while numbering the events which one of the following statements is false?

Advertisements
Advertisements

प्रश्न

In a network while numbering the events which one of the following statements is false?

पर्याय

  • Event numbers should be unique.

  • Event numbering should be carried out on a sequential basis from left to right.

  • The initial event is numbered 0 or 1.

  • The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.

MCQ
Advertisements

उत्तर

The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.3 [पृष्ठ २५०]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.3 | Q 5 | पृष्ठ २५०

संबंधित प्रश्‍न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The critical path of the following network is


Which of the following is not correct?


The objective of network analysis is to


Network problems have the advantage in terms of project


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×