मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

Which of the following is not correct?

Advertisements
Advertisements

प्रश्न

Which of the following is not correct?

पर्याय

  • Objective that we aim to maximize or minimize

  • Constraints that we need to specify

  • Decision variables that we need to determine

  • Decision variables are to be unrestricted.

MCQ
Advertisements

उत्तर

Decision variables are to be unrestricted.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.3 [पृष्ठ २५१]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.3 | Q 10 | पृष्ठ २५१

संबंधित प्रश्‍न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


In constructing the network which one of the following statements is false?


The objective of network analysis is to


Network problems have the advantage in terms of project


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×