Advertisements
Advertisements
प्रश्न
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
Advertisements
उत्तर

E1 = 0
E2 = 0 + 6 = 6
E3 = 0 + 5 = 5
E4 = 6 + 10 = 16
E5 = (5 + 4) or (16 + 6)
Whichever is maximum
= 22
E6 = (16 + 2) or (22 + 9)
Whichever is maximum
= 31
L6 = 31
L5 = 31 – 8 = 22
L4 = 22 – 6 = 16 or (31 – 2)
whichever is minimum
L3 = 22 – 4 = 18
L2 = 16 – 10 = 6
L1 = 6 – 6 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 6 | 0 | 6 | 6 – 6 = 0 | 6 |
| 1 - 3 | 5 | 0 | 5 | 18 – 5 = 13 | 18 |
| 2 - 4 | 10 | 6 | 16 | 16 – 10 = 6 | 16 |
| 3 - 4 | 3 | 5 | 8 | 16 – 3 = 13 | 16 |
| 3 - 5 | 4 | 5 | 9 | 22 – 4 = 18 | 22 |
| 4 - 5 | 6 | 16 | 22 | 22 – 6 = 16 | 22 |
| 4 - 6 | 2 | 16 | 18 | 31 – 2 = 29 | 31 |
| 5 - 6 | 9 | 22 | 31 | 31 – 9 = 22 | 31 |
Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.
APPEARS IN
संबंधित प्रश्न
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
Which of the following is not correct?
In the context of network, which of the following is not correct
The objective of network analysis is to
In critical path analysis, the word CPM mean
Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
