Advertisements
Advertisements
प्रश्न
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
Advertisements
उत्तर

E1 = 0
E2 = 0 + 6 = 6
E3 = 0 + 5 = 5
E4 = 6 + 10 = 16
E5 = (5 + 4) or (16 + 6)
Whichever is maximum
= 22
E6 = (16 + 2) or (22 + 9)
Whichever is maximum
= 31
L6 = 31
L5 = 31 – 8 = 22
L4 = 22 – 6 = 16 or (31 – 2)
whichever is minimum
L3 = 22 – 4 = 18
L2 = 16 – 10 = 6
L1 = 6 – 6 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 6 | 0 | 6 | 6 – 6 = 0 | 6 |
| 1 - 3 | 5 | 0 | 5 | 18 – 5 = 13 | 18 |
| 2 - 4 | 10 | 6 | 16 | 16 – 10 = 6 | 16 |
| 3 - 4 | 3 | 5 | 8 | 16 – 3 = 13 | 16 |
| 3 - 5 | 4 | 5 | 9 | 22 – 4 = 18 | 22 |
| 4 - 5 | 6 | 16 | 22 | 22 – 6 = 16 | 22 |
| 4 - 6 | 2 | 16 | 18 | 31 – 2 = 29 | 31 |
| 5 - 6 | 9 | 22 | 31 | 31 – 9 = 22 | 31 |
Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
| Activity | A | B | C | D | E | F | G | H | I | J | K |
| Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The critical path of the following network is

One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
