मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path

Advertisements
Advertisements

प्रश्न

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9
बेरीज
Advertisements

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 0 + 5 = 5

E4 = 6 + 10 = 16

E5 = (5 + 4) or (16 + 6)

Whichever is maximum

= 22

E6 = (16 + 2) or (22 + 9)

Whichever is maximum

 = 31

L6 = 31

L5 = 31 – 8 = 22

L4 = 22 – 6 = 16 or (31 – 2)

whichever is minimum

L3 = 22 – 4 = 18

L2 = 16 – 10 = 6

L1 = 6 – 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 – 6 = 0 6
1 - 3 5 0 5 18 – 5 = 13 18
2 - 4 10 6 16 16 – 10 = 6 16
3 - 4 3 5 8 16 – 3 = 13 16
3 - 5 4 5 9 22 – 4 = 18 22
4 - 5 6 16 22 22 – 6 = 16 22
4 - 6 2 16 18 31 – 2 = 29 31
5 - 6 9 22 31 31 – 9 = 22 31

Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 7 | पृष्ठ २४९

संबंधित प्रश्‍न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


In constructing the network which one of the following statements is false?


Network problems have the advantage in terms of project


In critical path analysis, the word CPM mean


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×