Advertisements
Advertisements
Question
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
Advertisements
Solution

E1 = 0
E2 = 0 + 6 = 6
E3 = 0 + 5 = 5
E4 = 6 + 10 = 16
E5 = (5 + 4) or (16 + 6)
Whichever is maximum
= 22
E6 = (16 + 2) or (22 + 9)
Whichever is maximum
= 31
L6 = 31
L5 = 31 – 8 = 22
L4 = 22 – 6 = 16 or (31 – 2)
whichever is minimum
L3 = 22 – 4 = 18
L2 = 16 – 10 = 6
L1 = 6 – 6 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 6 | 0 | 6 | 6 – 6 = 0 | 6 |
| 1 - 3 | 5 | 0 | 5 | 18 – 5 = 13 | 18 |
| 2 - 4 | 10 | 6 | 16 | 16 – 10 = 6 | 16 |
| 3 - 4 | 3 | 5 | 8 | 16 – 3 = 13 | 16 |
| 3 - 5 | 4 | 5 | 9 | 22 – 4 = 18 | 22 |
| 4 - 5 | 6 | 16 | 22 | 22 – 6 = 16 | 22 |
| 4 - 6 | 2 | 16 | 18 | 31 – 2 = 29 | 31 |
| 5 - 6 | 9 | 22 | 31 | 31 – 9 = 22 | 31 |
Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.
APPEARS IN
RELATED QUESTIONS
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
In constructing the network which one of the following statements is false?
Which of the following is not correct?
In the context of network, which of the following is not correct
Network problems have the advantage in terms of project
Draw a network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G | H | I | J | K |
| Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
