Advertisements
Advertisements
Question
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
| Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
| Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
Advertisements
Solution

E1 = 0
E2 = 0 + 6 = 6
E3 = 0 + 5 = 5
E4 = 6 + 10 = 16
E5 = (5 + 4) or (16 + 6)
Whichever is maximum
= 22
E6 = (16 + 2) or (22 + 9)
Whichever is maximum
= 31
L6 = 31
L5 = 31 – 8 = 22
L4 = 22 – 6 = 16 or (31 – 2)
whichever is minimum
L3 = 22 – 4 = 18
L2 = 16 – 10 = 6
L1 = 6 – 6 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 6 | 0 | 6 | 6 – 6 = 0 | 6 |
| 1 - 3 | 5 | 0 | 5 | 18 – 5 = 13 | 18 |
| 2 - 4 | 10 | 6 | 16 | 16 – 10 = 6 | 16 |
| 3 - 4 | 3 | 5 | 8 | 16 – 3 = 13 | 16 |
| 3 - 5 | 4 | 5 | 9 | 22 – 4 = 18 | 22 |
| 4 - 5 | 6 | 16 | 22 | 22 – 6 = 16 | 22 |
| 4 - 6 | 2 | 16 | 18 | 31 – 2 = 29 | 31 |
| 5 - 6 | 9 | 22 | 31 | 31 – 9 = 22 | 31 |
Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.
APPEARS IN
RELATED QUESTIONS
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
| Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
The critical path of the following network is

One of the conditions for the activity (i, j) to lie on the critical path is
In a network while numbering the events which one of the following statements is false?
Which of the following is not correct?
In the context of network, which of the following is not correct
The objective of network analysis is to
In critical path analysis, the word CPM mean
