Advertisements
Advertisements
Question
In the context of network, which of the following is not correct
Options
A network is a graphical representation.
A project network cannot have multiple initial and final nodes
An arrow diagram is essentially a closed network
An arrow representing an activity may not have a length and shape
Advertisements
Solution
An arrow representing an activity may not have a length and shape
APPEARS IN
RELATED QUESTIONS
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The critical path of the following network is

One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
Network problems have the advantage in terms of project
