हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

In the context of network, which of the following is not correct - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

In the context of network, which of the following is not correct

विकल्प

  • A network is a graphical representation.

  • A project network cannot have multiple initial and final nodes

  • An arrow diagram is essentially a closed network

  • An arrow representing an activity may not have a length and shape

MCQ
Advertisements

उत्तर

An arrow representing an activity may not have a length and shape

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.3 [पृष्ठ २५१]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.3 | Q 11 | पृष्ठ २५१

संबंधित प्रश्न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


The objective of network analysis is to


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×