Advertisements
Advertisements
प्रश्न
The following table use the activities in a construction projects and relevant information
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
| Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Advertisements
उत्तर

E1 = 0
E2 = 22 + 0 = 22
E3 = (0 + 27) or (22 + 12)
Whichever is maximum
E3 = 34
E4 = (22 + 14) or (34 + 6)
Whichever is maximum
E4 = 40
E5 = 40 + 12 = 52
L5 = 32
L4 = 52 – 12 = 40
L3 = 40 – 6 = 34
L2 = (40 – 14) or (34 – 12)
whichever is minimum
= 22
L1 = 22 – 22 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 22 | 0 | 22 | 22 – 22 = 0 | 22 |
| 1 - 3 | 27 | 0 | 27 | 34 – 27 = 7 | 34 |
| 2 - 3 | 12 | 22 | 34 | 34 – 12 = 26 | 34 |
| 2 - 4 | 14 | 22 | 36 | 40 – 14 = 26 | 40 |
| 3 - 4 | 6 | 34 | 40 | 40 – 6 = 34 | 40 |
| 4 - 5 | 12 | 40 | 52 | 52 – 12 = 40 | 52 |
Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 4 and 4 - 5.
Hence the critical path is 1 - 2 - 3 - 4 - 5 and the duration of time taken is 52 days.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
In the context of network, which of the following is not correct
The objective of network analysis is to
Network problems have the advantage in terms of project
A Project has the following time schedule
| Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
| Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
