हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

A project schedule has the following characteristics Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10 Time 4 1 1 1 6 5 4 8 1 2 5 7 - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

योग
Advertisements

उत्तर

E1 = 0

E2 = 0 + 4 = 4

E3 = 0 + 1 = 1

E4 = 4 + 1 = 5

E5 = 1 + 6 = 7

E6 = 7 + 4 = 11

E7 = 8 + 7 = 15

E8 = 15 + 2 = 7

E9 = 5 + 5 = 10

E10 = 17 + 5 = 22

L7 = 31

L10 = 22

L9 = 22 – 7 = 15

L8 = 22 – 5 = 17

L7 = 17 – 2 = 15

L= 17 – 1 = 16

L5 = (16 – 4) or (15 – 8)

whichever is minimum = 7

L4 = 15 – 5 = 10

L3 = (10 – 1) or (7 – 6)

whichever is minimum = 1

L2 = 10 – 1 = 9

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 4 0 4 9 – 4 = 5 9
1 - 3 1 0 1 1 – 1 = 0 1
2 - 4 1 4 5 10 – 1 = 9 10
3 - 4 1 1 2 10 – 1 = 9 10
3 - 5 6 1 7 7 – 6 =1 7
4 - 9 5 5 10 15 – 5 =10 15
5 - 6 4 7 11 16  4 = 12 16
5 - 7 8 7 15 15 – 8 = 7 15
6 - 8 1 11 12 17 – 1 = 16 17
7 - 8 2 15 17 17 – 2 = 15 17
8 - 10 5 17 22 22 – 5 = 17 22
9 - 10 7 10 17 22 – 7 = 15 22

Since EFT and LFT is same on 1 - 3, 3 - 5, 5 - 7 and 7 - 8 and 8 - 10 the critical path is 1 - 3 - 5 - 7 - 8 - 10 and the duration is 22 time units.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 6 | पृष्ठ २४९

संबंधित प्रश्न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The critical path of the following network is


In a network while numbering the events which one of the following statements is false?


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×