हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

A project schedule has the following characteristics Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10 Time 4 1 1 1 6 5 4 8 1 2 5 7

Advertisements
Advertisements

प्रश्न

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

योग
Advertisements

उत्तर

E1 = 0

E2 = 0 + 4 = 4

E3 = 0 + 1 = 1

E4 = 4 + 1 = 5

E5 = 1 + 6 = 7

E6 = 7 + 4 = 11

E7 = 8 + 7 = 15

E8 = 15 + 2 = 7

E9 = 5 + 5 = 10

E10 = 17 + 5 = 22

L7 = 31

L10 = 22

L9 = 22 – 7 = 15

L8 = 22 – 5 = 17

L7 = 17 – 2 = 15

L= 17 – 1 = 16

L5 = (16 – 4) or (15 – 8)

whichever is minimum = 7

L4 = 15 – 5 = 10

L3 = (10 – 1) or (7 – 6)

whichever is minimum = 1

L2 = 10 – 1 = 9

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 4 0 4 9 – 4 = 5 9
1 - 3 1 0 1 1 – 1 = 0 1
2 - 4 1 4 5 10 – 1 = 9 10
3 - 4 1 1 2 10 – 1 = 9 10
3 - 5 6 1 7 7 – 6 =1 7
4 - 9 5 5 10 15 – 5 =10 15
5 - 6 4 7 11 16  4 = 12 16
5 - 7 8 7 15 15 – 8 = 7 15
6 - 8 1 11 12 17 – 1 = 16 17
7 - 8 2 15 17 17 – 2 = 15 17
8 - 10 5 17 22 22 – 5 = 17 22
9 - 10 7 10 17 22 – 7 = 15 22

Since EFT and LFT is same on 1 - 3, 3 - 5, 5 - 7 and 7 - 8 and 8 - 10 the critical path is 1 - 3 - 5 - 7 - 8 - 10 and the duration is 22 time units.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 6 | पृष्ठ २४९

संबंधित प्रश्न

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The critical path of the following network is


One of the conditions for the activity (i, j) to lie on the critical path is


In constructing the network which one of the following statements is false?


Which of the following is not correct?


Network problems have the advantage in terms of project


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×