Advertisements
Advertisements
प्रश्न
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Advertisements
उत्तर

E1 = 0
E2 = 0 + 4 = 4
E3 = 0 + 1 = 1
E4 = 4 + 1 = 5
E5 = 1 + 6 = 7
E6 = 7 + 4 = 11
E7 = 8 + 7 = 15
E8 = 15 + 2 = 7
E9 = 5 + 5 = 10
E10 = 17 + 5 = 22
L7 = 31
L10 = 22
L9 = 22 – 7 = 15
L8 = 22 – 5 = 17
L7 = 17 – 2 = 15
L6 = 17 – 1 = 16
L5 = (16 – 4) or (15 – 8)
whichever is minimum = 7
L4 = 15 – 5 = 10
L3 = (10 – 1) or (7 – 6)
whichever is minimum = 1
L2 = 10 – 1 = 9
L1 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 4 | 0 | 4 | 9 – 4 = 5 | 9 |
| 1 - 3 | 1 | 0 | 1 | 1 – 1 = 0 | 1 |
| 2 - 4 | 1 | 4 | 5 | 10 – 1 = 9 | 10 |
| 3 - 4 | 1 | 1 | 2 | 10 – 1 = 9 | 10 |
| 3 - 5 | 6 | 1 | 7 | 7 – 6 =1 | 7 |
| 4 - 9 | 5 | 5 | 10 | 15 – 5 =10 | 15 |
| 5 - 6 | 4 | 7 | 11 | 16 4 = 12 | 16 |
| 5 - 7 | 8 | 7 | 15 | 15 – 8 = 7 | 15 |
| 6 - 8 | 1 | 11 | 12 | 17 – 1 = 16 | 17 |
| 7 - 8 | 2 | 15 | 17 | 17 – 2 = 15 | 17 |
| 8 - 10 | 5 | 17 | 22 | 22 – 5 = 17 | 22 |
| 9 - 10 | 7 | 10 | 17 | 22 – 7 = 15 | 22 |
Since EFT and LFT is same on 1 - 3, 3 - 5, 5 - 7 and 7 - 8 and 8 - 10 the critical path is 1 - 3 - 5 - 7 - 8 - 10 and the duration is 22 time units.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
| Activity | A | B | C | D | E | F | G | H | I | J | K |
| Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The critical path of the following network is

In constructing the network which one of the following statements is false?
In the context of network, which of the following is not correct
The objective of network analysis is to
In critical path analysis, the word CPM mean
