Advertisements
Advertisements
प्रश्न
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Advertisements
उत्तर

E1 = 0
E2 = 0 + 4 = 4
E3 = 0 + 1 = 1
E4 = 4 + 1 = 5
E5 = 1 + 6 = 7
E6 = 7 + 4 = 11
E7 = 8 + 7 = 15
E8 = 15 + 2 = 7
E9 = 5 + 5 = 10
E10 = 17 + 5 = 22
L7 = 31
L10 = 22
L9 = 22 – 7 = 15
L8 = 22 – 5 = 17
L7 = 17 – 2 = 15
L6 = 17 – 1 = 16
L5 = (16 – 4) or (15 – 8)
whichever is minimum = 7
L4 = 15 – 5 = 10
L3 = (10 – 1) or (7 – 6)
whichever is minimum = 1
L2 = 10 – 1 = 9
L1 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 4 | 0 | 4 | 9 – 4 = 5 | 9 |
| 1 - 3 | 1 | 0 | 1 | 1 – 1 = 0 | 1 |
| 2 - 4 | 1 | 4 | 5 | 10 – 1 = 9 | 10 |
| 3 - 4 | 1 | 1 | 2 | 10 – 1 = 9 | 10 |
| 3 - 5 | 6 | 1 | 7 | 7 – 6 =1 | 7 |
| 4 - 9 | 5 | 5 | 10 | 15 – 5 =10 | 15 |
| 5 - 6 | 4 | 7 | 11 | 16 4 = 12 | 16 |
| 5 - 7 | 8 | 7 | 15 | 15 – 8 = 7 | 15 |
| 6 - 8 | 1 | 11 | 12 | 17 – 1 = 16 | 17 |
| 7 - 8 | 2 | 15 | 17 | 17 – 2 = 15 | 17 |
| 8 - 10 | 5 | 17 | 22 | 22 – 5 = 17 | 22 |
| 9 - 10 | 7 | 10 | 17 | 22 – 7 = 15 | 22 |
Since EFT and LFT is same on 1 - 3, 3 - 5, 5 - 7 and 7 - 8 and 8 - 10 the critical path is 1 - 3 - 5 - 7 - 8 - 10 and the duration is 22 time units.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
The following table gives the activities of a project and their duration in days
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
| Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
A Project has the following time schedule
| Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
| Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
| Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
In constructing the network which one of the following statements is false?
Which of the following is not correct?
In the context of network, which of the following is not correct
Network problems have the advantage in terms of project
Draw a network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G | H | I | J | K |
| Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
