मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

A Project has the following time schedule Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8 Duration (in days) 7 6 14 5 11 7 11 4 18 Construct the network and calculate

Advertisements
Advertisements

प्रश्न

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

बेरीज
Advertisements

उत्तर

E1 = 0

E2 = 0 + 7 = 7

E3 = 7 + 14 = 21

E4 = 7 + 5 = 12

E5 = 21 + 11 or (12 + 7)

Whichever is maximum

= 32

E6 = 0 + 6 = 6

E7 = 6 + 11 = 17

E8 = 17 + 18 = 35

L8 = 35

L7 = 35 – 18 = 17

L6 = 17 – 11 = 6

L5 = 35 – 4 = 31

L4 = 32 – 7 = 25

L3 = 32 – 11 = 21

L2 = (21 – 14) or (25 – 5)

whichever is minimum

= 7

L1 = 7 – 7 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 7 0 7 7 – 7 = 0 7
1 - 6 6 0 6 7 – 6 = 1 7
2 - 3 14 7 21 21 – 14 = 7 21
2 - 4 5 7 12 25 – 5 = 20 25
3 - 5 11 21 32 31 – 11 = 21 32
4 - 5 7 12 19 32 – 25 = 7 14
6 - 7 11 6 17 18 – 11 = 7 18
5 - 8 4 32 36 36 – 4 = 32 36
7 - 8 18 17 36 36 – 18 = 18 36

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 8.

Hence the critical path is 1 - 2 - 3 - 5 - 8 and the duration of time taken is 36 days.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 9 | पृष्ठ २४९

संबंधित प्रश्‍न

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The critical path of the following network is


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×