Advertisements
Advertisements
प्रश्न
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Advertisements
उत्तर

E1 = 0
E2 = 0 + 5 = 5
E3 = (5 + 3) or (0 + 10)
Whichever is maximum
= 10
E4 = 10 + 4 = 14
E5 = 10 + 6 = 16
E6 = (14 + 6) or (16 + 5)
Whichever is maximum
= 21
E7 = 21 + 5 = 26
L7 = 26
L6 = 26 − 5 = 21
L5 = 21 − 5 = 16
L4 = 21 − 6 = 15
L3 = (15 − 4) or (16 − 6)
Whichever is minimum
= 10
L2 = 10 − 3 = 7
L1 = (7 − 5) or (10 − 10)
Whichever is minimum
L1 = 0
| Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
| 1 - 2 | 5 | 0 | 5 | 7 − 5 = 2 | 7 |
| 1 - 3 | 10 | 0 | 10 | 10 − 10 = 0 | 10 |
| 2 - 3 | 3 | 5 | 8 | 10 − 3 = 7 | 10 |
| 3 - 4 | 4 | 10 | 14 | 15 − 4 = 11 | 15 |
| 3 - 5 | 6 | 10 | 16 | 16 − 6 = 10 | 16 |
| 4 - 6 | 6 | 14 | 20 | 21 − 6 = 15 | 21 |
| 5 - 6 | 5 | 16 | 21 | 21 − 5 = 16 | 21 |
| 6 - 7 | 5 | 21 | 26 | 26 − 5 = 21 | 26 |
Since EFT and LFT values are same in 1 - 3, 3 - 5, 5 - 6 and 6 - 7.
Hence the critical path is 1 - 3 - 5 - 6 - 7 and the duration of time taken is 26 days.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
The critical path of the following network is

One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
In the context of network, which of the following is not correct
The objective of network analysis is to
Network problems have the advantage in terms of project
Draw a network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G | H | I | J | K |
| Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
