हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

The following table gives the characteristics of the project Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7 Duration(in days) 5 10 3 4 6 6 5 5 Draw the network for the project, - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

योग
Advertisements

उत्तर

E1 = 0

E2 = 0 + 5 = 5

E3 = (5 + 3) or (0 + 10)

Whichever is maximum

= 10

E4 = 10 + 4 = 14

E5 = 10 + 6 = 16

E6 = (14 + 6) or (16 + 5)

Whichever is maximum

= 21

E7 = 21 + 5 = 26

L7 = 26

L6 = 26 − 5 = 21

L5 = 21 − 5 = 16

L4 = 21 − 6 = 15

L3 = (15 − 4) or (16 − 6)

Whichever is minimum

= 10

L2 = 10 − 3 = 7

L1 = (7 − 5) or (10 − 10)

Whichever is minimum

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 5 0 5 7 − 5 = 2 7
1 - 3 10 0 10 10 − 10 = 0 10
2 - 3 3 5 8 10 − 3 = 7 10
3 - 4 4 10 14 15 − 4 = 11 15
3 - 5 6 10 16 16 − 6 = 10 16
4 - 6 6 14 20 21 − 6 = 15 21
5 - 6 5 16 21 21 − 5 = 16 21
6 - 7 5 21 26 26 − 5 = 21 26

Since EFT and LFT values are same in 1 - 3, 3 - 5, 5 - 6 and 6 - 7.

Hence the critical path is 1 - 3 - 5 - 6 - 7 and the duration of time taken is 26 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Miscellaneous Problems [पृष्ठ २५२]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Miscellaneous Problems | Q 10 | पृष्ठ २५२

संबंधित प्रश्न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


In constructing the network which one of the following statements is false?


In the context of network, which of the following is not correct


In critical path analysis, the word CPM mean


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×