मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

A Project has the following time schedule Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6 Duration(in days) 6 8 4 9 2 7

Advertisements
Advertisements

प्रश्न

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

बेरीज
Advertisements

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 6 + 8 = 14

E4 = 6 + 4 = 10

E5 = 14 + 9 = 23

E6 = (23 + 7) or (10 + 2)

Whichever is maximum

= 30

L6 = 30

L5 = 30 − 6 = 24

L4 = 30 − 2 = 28

L3 = 23 − 9 = 14

L2 = (14 − 8) or (28 − 4)

Whichever is minimum

= 6

L1 = 6 − 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 − 6 = 0 6
2 - 3 8 6 14 14 − 8 = 6 14
2 - 4 4 6 10 28 − 4 = 24 28
3 - 5 9 14 23 23 − 9 = 14 23
4 - 6 2 10 22 30 − 28 = 2 4
5 - 6 7 23 30 30 − 7 = 23 30

Since EFT and LFT values are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 6.

Hence the critical path is 1 - 2 - 3 - 5 - 6 and the duration of time taken is 30 days.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Miscellaneous Problems [पृष्ठ २५२]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Miscellaneous Problems | Q 9 | पृष्ठ २५२

संबंधित प्रश्‍न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The critical path of the following network is


Which of the following is not correct?


In the context of network, which of the following is not correct


Network problems have the advantage in terms of project


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×