हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path

Advertisements
Advertisements

प्रश्न

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9
योग
Advertisements

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 0 + 5 = 5

E4 = 6 + 10 = 16

E5 = (5 + 4) or (16 + 6)

Whichever is maximum

= 22

E6 = (16 + 2) or (22 + 9)

Whichever is maximum

 = 31

L= 31

L5 = 31 – 8 = 22

L4 = 22 – 6 = 16 or (31 – 2)

whichever is minimum

L3 = 22 – 4 = 18

L2 = 16 – 10 = 6

L1 = 6 – 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 – 6 = 0 6
1 - 3 5 0 5 18 – 5 = 13 18
2 - 4 10 6 16 16 – 10 = 6 16
3 - 4 3 5 8 16 – 3 = 13 16
3 - 5 4 5 9 22 – 4 = 18 22
4 - 5 6 16 22 22 – 6 = 16 22
4 - 6 2 16 18 31 – 2 = 29 31
5 - 6 9 22 31 31 – 9 = 22 31

Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 7 | पृष्ठ २४९

संबंधित प्रश्न

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The critical path of the following network is


In constructing the network which one of the following statements is false?


In a network while numbering the events which one of the following statements is false?


The objective of network analysis is to


In critical path analysis, the word CPM mean


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×