हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

Which of the following is not correct?

Advertisements
Advertisements

प्रश्न

Which of the following is not correct?

विकल्प

  • Objective that we aim to maximize or minimize

  • Constraints that we need to specify

  • Decision variables that we need to determine

  • Decision variables are to be unrestricted.

MCQ
Advertisements

उत्तर

Decision variables are to be unrestricted.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.3 [पृष्ठ २५१]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.3 | Q 10 | पृष्ठ २५१

संबंधित प्रश्न

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The critical path of the following network is


One of the conditions for the activity (i, j) to lie on the critical path is


The objective of network analysis is to


Network problems have the advantage in terms of project


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×