English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

The following table gives the activities of a project and their duration in days Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5 Duration 5 8 6 7 5 4 8 Construct the network and calculat - Business Mathematics and Statistics

Advertisements
Advertisements

Question

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Sum
Advertisements

Solution

E1 = 0

E2 = 0 + 5 = 5

E3 = (0 + 8) or (5 + 6)

Whichever is maximum

= 11

E4 = (11 + 5) or (5 + 7)

Whichever is maximum

= 16

E5 = (11 + 4) or (16 + 8)

Whichever is maximum

= 24

L5 = 24

L4 = 24 – 8 = 16

L3 = (24 – 4) or (16 – 5)

whichever is minimum

= 11

L2 = (16 – 6) or (16 – 7)

whichever is minimum

= 5

L1 = (5 – 5) or (11 – 8)

whichever is minimum

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 5 0 5 5 – 5 = 0 5
1 - 3 8 0 8 11 – 8 = 3 11
2 - 3 6 5 11 11 – 6 = 5 11
2 - 4 7 5 12 16 – 7 = 9 16
3 - 4 5 11 16 16 – 5 = 11 16
3 - 5 4 11 15 24 – 4 = 20 24
4 - 5 8 16 24 24 – 8 = 16 24

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 4 and 4 - 5.

Hence the critical path is 1 - 2 - 3 - 4 - 5 and the duration time taken is 24 days.

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 249]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 8 | Page 249

RELATED QUESTIONS

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


In constructing the network which one of the following statements is false?


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


The objective of network analysis is to


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×