Advertisements
Advertisements
प्रश्न
Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 3 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
Advertisements
उत्तर
Step 1: Row minimum
Subtract the smallest element in each row from every element in its row.
∴ The matrix obtained is given below:
| I | II | III | IV | V | |
| 1 | 5 | 0 | 4 | 13 | 6 |
| 2 | 7 | 3 | 0 | 6 | 8 |
| 3 | 1 | 0 | 2 | 2 | 3 |
| 4 | 9 | 0 | 3 | 8 | 6 |
| 5 | 5 | 0 | 8 | 13 | 4 |
Step 2: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.
| I | II | III | IV | V | |
| 1 | 4 | 0 | 4 | 11 | 3 |
| 2 | 6 | 3 | 0 | 4 | 5 |
| 3 | 0 | 0 | 2 | 0 | 0 |
| 4 | 8 | 0 | 3 | 6 | 3 |
| 5 | 4 | 0 | 8 | 11 | 1 |
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
| I | II | III | IV | V | |
| 1 | 4 | `cancel0` | 4 | 11 | 3 |
| 2 | `cancel6` | `cancel3` | `cancel0` | `cancel4` | `cancel5` |
| 3 | `cancel0` | `cancel0` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 8 | `cancel0` | 3 | 6 | 3 |
| 5 | 4 | `cancel0` | 8 | 11 | 1 |
Step 4: From step 3, minimum number of lines covering all the zeros are 3, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 3 | 0 | 3 | 10 | 2 |
| 2 | 6 | 4 | 0 | 4 | 5 |
| 3 | 0 | 1 | 2 | 0 | 0 |
| 4 | 7 | 0 | 2 | 5 | 2 |
| 5 | 3 | 0 | 7 | 10 | 0 |
Step 5: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | 3 | `cancel0` | 3 | 10 | 2 |
| 2 | `cancel6` | `cancel4` | `cancel0` | `cancel4` | `cancel5` |
| 3 | `cancel0` | `cancel1` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 7 | `cancel0` | 2 | 5 | 2 |
| 5 | `cancel3` | `cancel0` | `cancel7` | `cancel10` | `cancel0` |
Step 6: From step 5, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 2 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 1 | 0 | 1 | 8 | 0 |
| 2 | 6 | 6 | 0 | 4 | 5 |
| 3 | 0 | 3 | 2 | 0 | 0 |
| 4 | 5 | 0 | 0 | 3 | 0 |
| 5 | 3 | 2 | 7 | 10 | 0 |
Step 7: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | 1 | `cancel0` | `cancel1` | 8 | `cancel0` |
| 2 | 6 | `cancel6` | `cancel0` | 4 | `cancel5` |
| 3 | `cancel0` | `cancel3` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 5 | `cancel0` | `cancel0` | 3 | `cancel0` |
| 5 | 3 | `cancel2` | `cancel7` | 10 | `cancel0` |
Step 8: From step 7, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e.,5.
∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 0 | 0 | 1 | 7 | 0 |
| 2 | 5 | 6 | 0 | 3 | 5 |
| 3 | 0 | 4 | 3 | 0 | 1 |
| 4 | 4 | 0 | 0 | 2 | 0 |
| 5 | 2 | 2 | 7 | 9 | 0 |
Step 9: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | `cancel0` | `cancel0` | `cancel1` | `cancel7` | `cancel0` |
| 2 | 5 | 6 | `cancel0` | 3 | `cancel5` |
| 3 | `cancel0` | `cancel4` | `cancel3` | `cancel0` | `cancel1` |
| 4 | `cancel4` | `cancel0` | `cancel0` | `cancel2` | `cancel0` |
| 5 | 2 | 2 | `cancel7` | 9 | `cancel0` |
Step 10: From step 9, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.
∴ Select a row with exactly one zero, enclose that zero in ( ) and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ( ).
∴ The matrix obtained is as follows:
| I | II | III | IV | V | |
| 1 | 0 | `cancel0` | 1 | 7 | `cancel0` |
| 2 | 5 | 6 | 0 | 3 | 5 |
| 3 | `cancel0` | 4 | 3 | 0 | 1 |
| 4 | 4 | 0 | `cancel0` | 2 | `cancel0` |
| 5 | 2 | 2 | 7 | 9 | 0 |
Step 11: The matrix obtained in step 10 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:
| Jobs | Wagons | Mileage |
| 1 | I | 10 |
| 2 | II | 6 |
| 3 | III | 4 |
| 4 | IV | 9 |
| 5 | V | 10 |
∴ Total minimum mileage = 10 + 6 = 4 + 9 + 10 = 39.
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
| Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
| Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
| MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
The objective of an assignment problem is to assign ______.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 175 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
Choose the correct alternative:
Assignment Problem is special case of ______
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
Choose the correct alternative:
The assignment problem is said to be balanced if ______
If the given matrix is ______ matrix, the assignment problem is called balanced problem
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
What is the Assignment problem?
Give mathematical form of Assignment problem
What is the difference between Assignment Problem and Transportation Problem?
Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.
| Machine | ||||
| U | V | W | ||
| Jobs | A | 17 | 25 | 31 |
| B | 10 | 25 | 16 | |
| C | 12 | 14 | 11 | |
(cost is in ₹ per unit)
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Find the optimal solution for the assignment problem with the following cost matrix.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 11 | 17 | 8 | 16 | |
| Salesman | Q | 9 | 7 | 12 | 6 |
| R | 13 | 16 | 15 | 12 | |
| S | 14 | 10 | 12 | 11 | |
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
The solution for an assignment problem is optimal if
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?
| Workers | Packing of | |||
| Books | Toys | Crockery | Cutlery | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 12 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
