Advertisements
Advertisements
प्रश्न
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Advertisements
उत्तर
Here the number of rows and columns are equal.
∴ The given assignment problem is balanced.
Step 1: Select the smallest element in each row and subtract this from all the elements in its row.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 40 | 20 | 0 |
| 2 | 0 | 10 | 30 | |
| 3 | 0 | 30 | 10 | |
Step 2: Select the smallest element in each column and subtract this from all the elements in its column.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 40 | 10 | 0 |
| 2 | 0 | 0 | 30 | |
| 3 | 0 | 20 | 10 | |
Step 3: Examine the rows with exactly one zero, mark the zero by □. Mark other zeros in its column by X.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 40 | 10 | 0 |
| 2 | 0 | 0 | 30 | |
| 3 | 0 | 20 | 10 | |
Step 4: Now examine the columns with exactly one zero mark the zero by □.
Mark other zeros in its row by X.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 40 | 10 | 0 |
| 2 | 0 | 0 | 30 | |
| 3 | 0 | 20 | 10 | |
Thus all the three assignment have been made.
The optimal assignment schedule and total cost is
| Programmers | Programmes | Cost |
| 1 | R | 80 |
| 2 | Q | 90 |
| 3 | P | 110 |
| Total Cost | 280 | |
The optimal assignment (minimum) cost = ₹ 280.
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
The assignment problem is said to be unbalance if ______
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Fill in the blank :
When an assignment problem has more than one solution, then it is _______ optimal solution.
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
What is the Assignment problem?
Choose the correct alternative:
Number of basic allocation in any row or column in an assignment problem can be
Choose the correct alternative:
North – West Corner refers to ______
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
| a | b | c | d | e | |
| A | 160 | 130 | 175 | 190 | 200 |
| B | 135 | 120 | 130 | 160 | 175 |
| C | 140 | 110 | 155 | 170 | 185 |
| D | 50 | 50 | 80 | 80 | 110 |
| E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
