English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 12

A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be - Business Mathematics and Statistics

Advertisements
Advertisements

Question

A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.

  Programmers
    P Q R
Programmers 1 120 100 80
  2 80 90 110
  3 110 140 120

Assign the programmers to the programme in such a way that the total computer time is least.

Chart
Sum
Advertisements

Solution

Here the number of rows and columns are equal.

∴ The given assignment problem is balanced.

Step 1: Select the smallest element in each row and subtract this from all the elements in its row.

  Programmers
    P Q R
Programmers 1 40 20 0
  2 0 10 30
  3 0 30 10

Step 2: Select the smallest element in each column and subtract this from all the elements in its column.

  Programmers
    P Q R
Programmers 1 40 10 0
  2 0 0 30
  3 0 20 10

Step 3: Examine the rows with exactly one zero, mark the zero by □. Mark other zeros in its column by X.

  Programmers
    P Q R
Programmers 1 40 10 0
  2 0 0 30
  3 0 20 10

Step 4: Now examine the columns with exactly one zero mark the zero by □.

Mark other zeros in its row by X.

  Programmers
    P Q R
Programmers 1 40 10 0
  2 0 0 30
  3 0 20 10

Thus all the three assignment have been made.

The optimal assignment schedule and total cost is

Programmers Programmes Cost
1 R 80
2 Q 90
3 P 110
Total Cost 280

The optimal assignment (minimum) cost = ₹ 280.

shaalaa.com
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 256]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 12 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 5 | Page 256

RELATED QUESTIONS

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 31 25 33 29
B 25 24 23 21
C 19 21 23 24
D 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


Choose the correct alternative:

The assignment problem is said to be balanced if ______


Choose the correct alternative:

Number of basic allocation in any row or column in an assignment problem can be


Choose the correct alternative:

The purpose of a dummy row or column in an assignment problem is to


A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 170
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?


A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?

Workers Packing of
  Books Toys Crockery Cutlery
A 3 11 10 8
B 13 2 12 12
C 3 4 6 1
D 4 15 4 9

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×