Advertisements
Advertisements
Question
What is the difference between Assignment Problem and Transportation Problem?
Advertisements
Solution
The assignment problem is a special case of the transportation problem.
The differences are given below:
| Transportation Problem | Assignment Problem |
| 1. This is about reducing the cost of transportation merchandise | 1. This is about assigning finite sources to finite destinations where only one destination is allotted for one source with a minimum cost |
| 2. Number of sources and number of demand need not be equal | 2. Number of sources and the number of destinations must be equal |
| 3. If total demand and total supply are not equal then the problem is said to be unbalanced. | 3. If the number of rows is not equal to the number of columns then problems are unbalanced. |
| 4. It requires 2 stages to solve: Getting initial basic feasible solution, by NWC, LCM, VAM and optimal solution by MODI method | 4. It has only one stage. Hungarian method is sufficient for obtaining an optimal solution |
APPEARS IN
RELATED QUESTIONS
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
| Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
| Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
| MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
The assignment problem is said to be unbalance if ______
The objective of an assignment problem is to assign ______.
Fill in the blank :
An _______ is a special type of linear programming problem.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
| I | II | III | IV | |
| A | 7 | 25 | 26 | 10 |
| B | 12 | 27 | 3 | 25 |
| C | 37 | 18 | 17 | 14 |
| D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
