Advertisements
Advertisements
प्रश्न
What is the difference between Assignment Problem and Transportation Problem?
Advertisements
उत्तर
The assignment problem is a special case of the transportation problem.
The differences are given below:
| Transportation Problem | Assignment Problem |
| 1. This is about reducing the cost of transportation merchandise | 1. This is about assigning finite sources to finite destinations where only one destination is allotted for one source with a minimum cost |
| 2. Number of sources and number of demand need not be equal | 2. Number of sources and the number of destinations must be equal |
| 3. If total demand and total supply are not equal then the problem is said to be unbalanced. | 3. If the number of rows is not equal to the number of columns then problems are unbalanced. |
| 4. It requires 2 stages to solve: Getting initial basic feasible solution, by NWC, LCM, VAM and optimal solution by MODI method | 4. It has only one stage. Hungarian method is sufficient for obtaining an optimal solution |
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
| Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
| Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
| MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
The assignment problem is said to be unbalance if ______
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
What is the Assignment problem?
Find the optimal solution for the assignment problem with the following cost matrix.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 11 | 17 | 8 | 16 | |
| Salesman | Q | 9 | 7 | 12 | 6 |
| R | 13 | 16 | 15 | 12 | |
| S | 14 | 10 | 12 | 11 | |
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
