A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table

Advertisements
Advertisements

प्रश्न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?

योग
Advertisements

उत्तर

We can express the matrix form

`[(31,25,33,29), (25,24,23,21), (19,21,23,24), (38,36,34,40)]`

Subtracting the smallest element in each row from every element of it,

`[(6,0,8,4), (4,3,2,0), (0,2,4,5), (4,2,0,6)]`

Subtracting the smallest element In each column from very element of it.

`[(6,0,8,4), (4,3,2,0), (0,2,4,5), (4,2,0,6)]`

All the zeros of the above matrix are covered with minimum number of lines as below :

No. of lines = No. of rows/columns

Assignment of jobs :

A → Q, B → S, C → P, D → R

Minimum cost = 25 + 21 + 19 + 34

                        = Rs 99

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
2014-2015 (March)

APPEARS IN

वीडियो ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्न

Solve the following minimal assignment problem and hence find the minimum value : 

  I II III IV
A 2 10 9 7
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

 


Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52

Solve the following maximal assignment problem :

Branch Manager Monthly Business ( Rs. lakh)
A B C D
P 11 11 9 9
Q 13 16 11 10
R 12 17 13 8
S 16 14 16 12

 


A departmental head has three jobs and four subordinates. The subordinates differ in their capabilities and the jobs differ in their work
contents. With the help of the performance matrix given below, find out which of the four subordinates should be assigned which jobs ?

Subordinates Jobs
I II III
A 7 3 5
B 2 7 4
C 6 5 3
D 3 4 7

Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

The assignment problem is said to be unbalance if ______


The assignment problem is said to be balanced if ______.


Choose the correct alternative :

In an assignment problem if number of rows is greater than number of columns then


In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.


State whether the following is True or False :

In assignment problem, each facility is capable of performing each task.


Choose the correct alternative:

The assignment problem is generally defined as a problem of ______


In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added


State whether the following statement is True or False: 

In assignment problem each worker or machine is assigned only one job


What is the Assignment problem?


What is the difference between Assignment Problem and Transportation Problem?


A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.

  Programmers
    P Q R
Programmers 1 120 100 80
  2 80 90 110
  3 110 140 120

Assign the programmers to the programme in such a way that the total computer time is least.


Choose the correct alternative:

Number of basic allocation in any row or column in an assignment problem can be


Choose the correct alternative:

North – West Corner refers to ______


A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:

  I II III IV
A 3 11 10 8
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

Complete the following activity to allocate tasks to subordinates to minimize total time.

Solution:

Step I: Subtract the smallest element of each row from every element of that row:

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Step II: Since all column minimums are zero, no need to subtract anything from columns.

Step III: Draw the minimum number of lines to cover all zeros.

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Since minimum number of lines = order of matrix, optimal solution has been reached

Optimal assignment is A →`square`  B →`square`

C →IV  D →`square`

Total minimum time = `square` hours.